LAHORE: The Punjab government has approved funds for construction of the Multan metro project.
The approval was granted in a recent meeting at  Planning and Development Department, a senior official of P&D told APP here on Sunday. Presenting details, he said Multan Metro Project Corridor-I included: BZU to Kumharan Chowk passing through the Major Intersections of Northern Bypass, Chungi No.6, Chungi No.9, Fish Market, Daulat Gate, Chungi No.14, BCG Chowk and Vehari Chowk, Approximate length=18 km. (Package 1: Bahauddin Zakaria University to Chungi No.6, length= 5.625 km) at a cost of Rs 4097.19 million.
BZU to Kumharan Chowk passing through the Major Intersections of Northern Bypass, Chungi No.6, Chungi No.9, Fish Market, Daulat Gate, Chungi No.14, BCG Chowk and Vehari Chowk, Approximate length=18 km. (Package 2: Chungi No.6 to Fish Market, length=3.273 km) at a cost of Rs 3905.60 million, Construction of Multan Metro Project Corridor-I: BZU to Kumharan Chowk passing through Major Intersections of Northern Bypass, Chungi No.6, Chungi No.9, Fish Market, Daulat Gate, Chungi No.14, BCG Chowk and Vehari Chowk, Approximate length=18 km. (Package 3:Fish Market to Chungi No.14, length=1.171 km) at a cost of Rs. 2801.95 million, BZU to Kumharan Chowk passing through the Major Intersections of Northern Bypass, Chungi No.6, Chungi No.9, Fish Market, Daulat Gate, Chungi No.14, BCG Chowk and Vehari Chowk, Approximate length=18 Km. (Package 4: Chungi No.14 to BCG Chowk and Segment of Vehari Road, length=2.331 km) at a cost of Rs. 3564.78 million.
BZU to Kumharan Chowk passing through the Major Intersections of Northern Bypass, Chungi No.6, Chungi No.9, Fish Market, Daulat Gate, Chungi No.14, BCG Chowk and Vehari Chowk, Approximate length=18 km. (Package 5: BCG Chowk to Chowk Kumharan, length=5.582 km) at a cost of Rs. 3773.94 million, Construction of Multan Metro Project Corridor-2: It starts from BCG Chowk and terminates at Chungi No. 9 passing through Shahbaz Chowk, Chowk Gala Gadaam, Double Phattak, SP Chowk, MBQ Chowk, Kalma Chowk, Katchery Chowk, and Chungi No.8, Approximate length=10.8 Km. (Package 6: BCG Chowk to Double Phatak, length=4.10 km) at a cost of Rs. 4044.23 million.
Construction of Multan Metro Project Corridor-2: It starts from BCG Chowk And terminates at Chungi No. 9 Passing through Shahbaz Chowk, Chowk Gala Gadaam, Double Phattak, SP Chowk, MBQ Chowk, Kalma Chowk, Katchery Chowk, and Chungi No.8, Approximate length=10.8 km. 
(Package 7: Shah Abbass Chowk to Muhammad Bin Qasim Chowk, length=3.9 km) at the cost of Rs. 3609.82 million. Construction of Multan Metro Project Corridor-2: It starts from BCG Chowk and terminates at Chungi No. 9 Passing Through Shahbaz Chowk, Chowk Gala Gadaam, Double Phattak, SP Chowk, MBQ Chowk, Kalma Chowk, Katchery Chowk, and Chungi No.8, Approximate length=10.8 km. 
(Package 8: Muhammad Bin Qasim Chowk to Chungi No.9, length=2.823 km) at a cost of Rs. 4553.95 million.
Construction of Multan Metro Project Corridor-2: (Extension): It starts from Double Phattak and terminates at Nagshah with Askari Chowk in between. Approximate length=7.57 km. (Package 9: Nagg Shah to Double Phattak, length=7.578 km) at a cost of Rs. 4344.73 million.
Construction of Multan Metro Project, Supply, Installation, Testing, Commissioning, Operation & Maintenance of Escalator & Elevators at the cost of Rs. 3205.01 million, Construction of Multan Metro Project, Supply, Installation, Testing, Commissioning, Operation & Maintenance of Solar Street Lights, Generators and Platform Screen Door (PSD) at a cost of Rs. 3035.88 million has also been approved, he said.